Shop to home conversion – Cassà de la Selva (Girona)
FIARCÓN delivered
FIARCÓN was the company responsible for the drylining systems used to convert 2 commercial units into 2 homes, installing approximately 485 m² of plasterboard.
Work carried out
Installation of double-board interior partitions, wall linings and suspended ceilings, incorporating TECSOUND acoustic insulation and adapting the systems to the new layout of the dwellings.
Project delivery
The installation of approximately 485 m² was completed in just 12 days by a team of 3 operatives, with efficient organisation and a steady pace of work.
Result
Two former commercial units ready for their new layout as dwellings, with approximately 485 m² of partitions, wall linings and ceilings installed, providing a solid base for the following finishing and services phases.