Shop to home conversion – Cassà de la Selva (Girona)

FIARCÓN delivered

FIARCÓN was the company responsible for the drylining systems used to convert 2 commercial units into 2 homes, installing approximately 485 m² of plasterboard.

Work carried out

Installation of double-board interior partitions, wall linings and suspended ceilings, incorporating TECSOUND acoustic insulation and adapting the systems to the new layout of the dwellings.

Project delivery

The installation of approximately 485 m² was completed in just 12 days by a team of 3 operatives, with efficient organisation and a steady pace of work.

Result

Two former commercial units ready for their new layout as dwellings, with approximately 485 m² of partitions, wall linings and ceilings installed, providing a solid base for the following finishing and services phases.

Cassa de la selva loca 1 (8).jpgLocales Cassa de la Selva, pladur Fiarcon (4).pngLocales Cassa de la Selva, pladur Fiarcon (1).pngLocales Cassa de la Selva, pladur Fiarcon (3).pngLocales Cassa de la Selva, pladur Fiarcon (2).pngLocales Cassa de la Selva, pladur Fiarcon (6).pngLocales Cassa de la Selva, pladur Fiarcon (7).pngLocales Cassa de la Selva, pladur Fiarcon (8).pngLocales Cassa de la Selva, pladur Fiarcon (5).pngCassa de la selva loca 1 (1).jpgCassa de la selva loca 1 (2).jpgCassa de la selva loca 1 (3).jpgCassa de la selva local 2 (3).jpgCassa de la selva local 2 (2).jpgCassa de la selva local 2 (1).jpgCassa de la selva loca 1 (4).jpgCassa de la selva loca 1 (5).jpgCassa de la selva loca 1 (6).jpgCassa de la selva loca 1 (7).jpgCassa de la selva local 2 (1).jpegPortada.png